2nd Floor Renovation: “PLEASE PARDON OUR DUST”

Good Day All,
“PLEASE PARDON Our DUST and PROGRESS”

NEW update on the progress of the Second-Floor hallway project.

Contractor was out this past week to install bulkhead at the Skylight (see the attached picture). 
The Electrical contractor has removed and lowered of the emergency elements below the projected new finish ceiling.

The new light fixtures arrive on-site the Week of March 11th, if not earlier, if the supply chain is not broken.    Additional flooring trim and transition materials could arrive week of March 25th.

The Contractor discussed the process to limit the disruption of the building usage by Staff, Rentals, Recovery Groups and Sunday morning services.

The Process
Installed wall/bulkhead at west end and skylight;
Moved the emergency elements down below the new ceiling line;
Install ceiling grid;
Install new lighting fixtures;
Install new flooring;
Install the new ceiling tiles;
Paint the walls and clove base.

Again, the Contractor(s) wanted to have all the building materials on-site, to reduce the disrupted construction period.  Other preparation work is being done in advance.

Thanks
Your UUCC Building & Grounds Team